Title: 25-204, Approve Change Order, 2025 MSBU Paving Program (Public Works)
Attachments: 1. 25-204 Change Order 3, 2. BA26-221 Rotonda West FY25 Paving, 3. Resolution BA26-221.pdf, 4. Rotonda Circle - Stability Information, 5. Rotonda Paving - Milling Rotonda Circle - 1.27.26, 6. Rotonda Circle - Marshal Stability_JL
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT MAKING REQUEST
Budget & Admin Services

Title
title
25-204, Approve Change Order, 2025 MSBU Paving Program (Public Works)
end
REQUESTED MOTION/ACTION

recommendation
Recommended Action:
a) Approve Change Order #3 for File #25-204, 2025 MSBU Paving Program, awarded to Ajax Paving Industries of Florida LLC of North Venice, Florida to increase amount $555,931.81. This change order is to add Reclaimed Base to one area and subtract Reclaimed Base from another, also to add milling on Rotonda Circle; and
b) Approve additional 120 days of contract time; and
c) Approve Resolution for budget adjustment BA26-221 in the amount of $555,932 increasing the MSBU Capital Maintenance Paving Program.
end
budget
Budgeted Action:
Approve budget adjustment BA26-221 in the amount of $555,932 to amend the MSBU Capital Maintenance Paving Program for Rotonda West. Funding is provided from Rotonda West Street and Drainage MSBU assessments.
end

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)
body
Background:
Public Works is requesting Change Order #3, to add Reclaimed Base to one area and subtract Reclaimed Base from another, also to add milling on Rotonda Circle. This change order increases the Contract amount $555,931.81, for an updated total cost of $17,610,063.81.

The original contract time was 249 days for completion. With the additional 120 days, the updated contract time is 369 days.

Original Bid Amount $17,054,132
Change Order #1 ($42,582) deductive request to remove 453 SY of 6" asphalt base repair - Pioneer Trail
Change Order #2 $42,582 reverses the deductive request to remove 453 SY of 6" asphalt base repair - Pioneer Trail
Change Order #3 $555,931.81
Updated Total Cost $17,610,063.81

Therefore, it is requested that the Charlotte County Board of County Commissioners approve Change Order #3 for File #25-204, 2025 MSBU Paving Program, awarded to Ajax Paving located in North Venice, Florida, to increase amount $555,931.81...