Legislation Details

File #: 2026-8715    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 9/21/2026 In control: Board of County Commissioners
On agenda: 10/27/2026 Final action:
Title: 26-407, Approve Contract, Design – Anger Fishing Pier (Community Services)
Attachments: 1. 26-407 Submittal Giffels Webster Engineers Inc, 2. 26-407 Original RFP, 3. Agreement Design-Anger Fishing Pier-Giffels-Webster FINAL
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

26-407, Approve Contract, Design - Anger Fishing Pier (Community Services)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve contract for Request for Proposal #26-407, Design - Anger Fishing Pier, to Giffels-Webster, of Englewood, Florida, in the amount of $269,700; and

b) Authorize the Chairman to sign.

end

budget

Budgeted Action:

No action needed. Funding for this hurricane Milton repair is being provided through the County’s general revenues and collected in the hurricane fund. There is an anticipated reimbursement of 75% from the Federal Emergency Management Agency, with a Florida Department of Emergency Management reimbursement of 12.5%, and a local match of 12.5%.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

Charlotte County is seeking professional design services for the design of construction ready plans to be incorporated into the County bid documents and all applicable Federal, State, and Local permitting and construction oversight services for the partial demolition and complete replacement/repair/revetment of the fishing pier, bulkhead and approach, located at Anger Fishing Pier.

 

On July 28, 2026, the Board of County Commissioners approved the ranking of firms, the approval to start negotiations, and authorized the Chairman to sign the contracts after completion of negotiations, if the contract did not exceed $225,000. As contract does exceed that amount, it is brought back to the Board for official review and approval.

 end