Title: 25-062, Approve Change Order, Kings Highway and Harborview Road Intersection Improvements (Public Works)
Attachments: 1. 25-062 Change Order #1 Board Approval, 2. 25-062 Change Order #2 Admin Approval, 3. 25-062 Change order #3 Admin Approval, 4. 25-062 Change Order #4 (this change order)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT MAKING REQUEST
Budget & Admin Services

Title
title
25-062, Approve Change Order, Kings Highway and Harborview Road Intersection Improvements (Public Works)
end
REQUESTED MOTION/ACTION

recommendation
Recommended Action:
Approve Change Order #4 to Request for Bid #25-062, Kings Highway and Harborview Road Intersection Improvements for an additional $147,282.87, which was awarded to Andrew Sitework LLC, of Fort Myers, Florida. This additional work is for repairs related to a truck accident at the intersection that damaged the newly installed traffic signal mast arm
end
budget
Budgeted Action:
No action needed. Budgeted in the Public Works Engineering budget as approved in the FY2027 budget process. Funding for the expenditure comes from MSTU. These expenditures will be reimbursed through the accident claims recovery process.
end

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)
body
Background:
The purpose of this bid is to secure the services of a licensed Contractor for intersection
improvements at Kings Highway and Harborview Road. The project includes milling and resurfacing, auxiliary lane widening, drainage improvements, signalization, intelligent transportation system improvements, lighting improvements, and signing and pavement markings as indicated on the construction plans.

Public Works is requesting Change Order #4 which is related to a truck accident at the intersection that damaged the newly installed traffic signal mast arm.

$1,435,486.95 Original Contract Amount
$ 99,377.77 Change Order #1 (Board Approved)
$ 7,505.38 Change Order #2 (Admin Approved)
$ 58,599.50 Change Order #3 (Admin Approved)
$ 147,282.87 This Change Order (#4)
$1,748,252.47 Revised Contract Total

Therefore, it is recommended to approve Change Order #4 to Request for Bid #25-062, Kings Highway and Harborview Road Intersection Improvements for an additional cost of $147,282.87, which was awarded to Andrew S...

Click here for full text