Title: FY2027 Midway and Abalom Gravity Sewer Outlet New Capital Improvement Project (CIP)
Attachments: 1. Resolution BA27-263, 2. 1 Justification- Midway & Abalom Gravity Sewer Outlet Proj Just, 3. c352701 Midway & Abalom Gravity Sewer Outlet, 4. BA27-263 Midway & Abalom Gravity Sewer Outlet
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Utilities

 

Title
title

FY2027 Midway and Abalom Gravity Sewer Outlet New Capital Improvement Project (CIP)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Resolution for budget adjustment BA27-263 in the amount of $205,000; and

b) Approve new Capital Improvement Project “Midway & Abalom Gravity Sewer Outlet”; and

c) Authorize staff to proceed with project design, permitting, bidding, and construction activities for the Midway and Abalom Gravity Sewer Outlet CIP.

end

budget

Budgeted Action:

Approve budget adjustment BA27-263 in the amount of $205,000 adding a new Capital Improvement Project “Midway & Abalom Gravity Sewer Outlet” to the adopted FY27 Capital Improvement Program. Funding will be provided from the Utility Wastewater Connection Fee Fund using reserves from Utility Operation and Maintenance Fund.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

The Midway & Abalom Gravity Sewer Outlet Project will provide a permanent connection for the existing isolated gravity sewer system serving residences along Midway Boulevard. The project includes the installation of a grinder pump station and related infrastructure necessary to connect the sewer line to the County’s wastewater collection system.

 

Completion of the project will eliminate the need for ongoing pump-out operations, improve the reliability of wastewater service, and reduce the potential for sanitary sewer overflows. Establishing a permanent connection will also support more efficient system operations and maintenance.

 

Staff recommend establishing the Midway & Abalom Gravity Sewer Outlet Project within the FY2027 Capital Improvement Program and appropriating $205,000 to fund design, permitting, bidding, and construction activities.

 

 

 end