DEPARTMENT MAKING REQUEST
Public Works
Title
title
Adopt New Capital Improvement Project “Mid County Transfer Roadway Reconfiguration”
end
REQUESTED MOTION/ACTION
recommendation
Recommended Action:
a) Approve Resolution for budget adjustment BA24-116 in the amount of $103,000; and
b) Approve adoption of a new Capital Improvement Project (CIP) “Mid County Transfer Roadway Reconfiguration”.
end
budget
Budgeted Action:
Approve budget adjustment BA24-116 in the amount of $103,000 creating a new Capital Improvement Project titled “Mid County Transfer Roadway Reconfiguration” in the FY24 Capital Improvement Program. Funding is provided from reserves in the Charlotte County Solid Waste Enterprise Fund.
end
BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)
body
Background:
This project is for safety and operational reasons. This new access point will provide the County’s semitrucks their own entrance eliminating the risk of accidents from co-mingling with facility customers. The new access will eliminate the existing problem of these trucks navigating between cars/people when they are in line to use the facility as well as customers who park and back up at the C.A.R.E. store and then drive against the flow of incoming traffic to exit from the current single access driveway. Providing the new access will allow the facility semitrucks to enter and leave the site without hindrance from other traffic.
end