Legislation Details

File #: 2024-6094    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 5/20/2024 In control: Board of County Commissioners
On agenda: 6/11/2024 Final action:
Title: 24-282, Award, Utility Main Installation Projects (Utilities)
Attachments: 1. 24-282 Bid Tabulation, 2. 24-282 Bidders Submittal, 3. 24-282 CCU14-0029 Cochran Blvd II, 4. 24-282 CCU22-0014 Foresman Water Main, 5. 24-282 CCU23-0006 FM to Barger on US 41, 6. 24-282 CCU23-0013 Burlington Ave Extend and Loop WM, 7. 24-282 CCU23-0013 Burlington Scrub Jay, 8. 24-282 CCU24-0001 Yorkshire WM, 9. 24-282 CCU24-0002 Sherbourne Street, 10. 24-282 CCUO-23-005 Higgs Drive FM Replacement, 11. Project White Paper, 12. c350602 Wastewater Force Mains Expansionary, 13. c339702 Major Water Transmission Lines, 14. c350902 Reclaimed Water Lines, 15. c332207 Water Main Toledo Blade Hillsb-US 41, 16. c332207 AMENDED Toledo Blade from Hillsborough to US 41 24 WM 5.28.24, 17. BA24-119 Utility Main Installation Projects (Utilities) 6.11.24, 18. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT MAKING REQUEST
Budget & Admin Services

Title
title
24-282, Award, Utility Main Installation Projects (Utilities)
end
REQUESTED MOTION/ACTION

recommendation
Recommended Action:
a) Approve award of Request for Bid, File #24-282, Utility Main Installation Projects, to the lowest responsive, responsible Bidder, Accurate Drilling Systems Incorporated of Labelle, Florida at the total cost of $6,070,299.90. This project is to complete the construction of a wastewater force main, reclaimed water main, and multiple potable water main installation projects at various locations; and
b) Approve Resolution for budget adjustment BA24-119 in the amount of $3,092,633 for Capital Improvement Project "Toledo Blade from Hillsborough to US 41"; and
c) Approve amending Capital Improvement Project "Toledo Blade from Hillsborough to US 41".
**Change, Added attachment - Resolution, 6/6/2024**
end
budget
Budgeted Action:
Approve budget adjustment BA24-119 in the amount of $3,092,633 adding additional funding to include mobilization and contingency for Capital Improvement Project "Toledo Blade from Hillsborough to US 41" increasing the budget from $1,048,850 to $4,141,483. Funding will come from Water Connection Fee fund reserves. Sufficient funding is available on the other associated Capital Improvement Projects "Wastewater Force Main Expansionary", "Reclaimed Water Lines", "Major Water Transmission Lines", and the Capital Maintenance Plan as approved in the FY24 budget process. Funding is supplied from the Utility Water Connection Fee fund, Utility Wastewater Connection Fee Fund, and the Utility Renewal and Replacement Fund.
end

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)
body
Background:
It is the intent of Charlotte County to secure the services of a Contractor to furnish all materials, labor, equipment, and all other appurtenances required to successfully complete the construction of a wastewater force main, reclaimed ...

Click here for full text