Legislation Details

File #: 2024-6165    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 6/21/2024 In control: Board of County Commissioners
On agenda: 7/9/2024 Final action:
Title: 24-420, Award, Englewood East MSBU Bridge Rehabilitations (Public Works)
Attachments: 1. 24-420 Bid Tabulation, 2. 24-420 Bidder's Submittal, 3. 24-420 Plans - Gulfstream Blvd over Sea Mist WW (Br. No 014091), 4. 24-420 Plans - Marathon Blvd over Sioux WW (Br. No 014084), 5. 24-420 Plans - Oceanspray Blvd over March WW (Br. No 014097), 6. 24-420 Plans - Wilmington Blvd over Gondolier WW (Br. No 014096), 7. 24-420 Plans- Gulfstream Blvd over Memorial WW (Br. No 014083)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT MAKING REQUEST
Budget & Admin Services

Title
title
24-420, Award, Englewood East MSBU Bridge Rehabilitations (Public Works)
end
REQUESTED MOTION/ACTION

recommendation
Recommended Action:
Approve award of Request for Bid #24-420, Englewood East MSBU Bridge Rehabilitations, to Villa-Fuerte Construction LLC of Arcadia, Florida for the total project amount of $1,047,835.95. This is for the bridge repairs on Gulfstream Boulevard over Memorial Waterway (Bridge #014083); Gulfstream Boulevard over Sea Mist Waterway (Bridge #014091); Marathon Boulevard over Sioux Waterway (Bridge #014084); Wilmington Boulevard over Gondolier Waterway (Bridge #014096); and Ocean Spray Boulevard over March Waterway (Bridge #014097).
end
budget
Budgeted Action:
No action needed. Budgeted in the Public Works MSBU/TU Bridges Capital Maintenance Plan as approved in the FY24 budget process. Funding is supplied from Englewood East Street and Drainage MSBU assessments.
end

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)
body
Background:
This is for the services of a Contractor to furnish all materials, labor, equipment, and all other appurtenances required to successfully complete minor repairs on five (5) bridges within the Englewood East MSBU area. The bridges are located on Gulfstream Boulevard over Memorial Waterway (Bridge #014083); Gulfstream Boulevard over Sea Mist Waterway (Bridge #014091); Marathon Boulevard over Sioux Waterway (Bridge #014084); Wilmington Boulevard over Gondolier Waterway (Bridge #014096); and Ocean Spray Boulevard over March Waterway (Bridge #014097). The work also includes all other items of construction including, but not limited to, removal and disposal of existing structures, construction of bridge railing, guardrail, site dewatering, excavation and fill, grading, sodding, and maintenance of traffic.

It has been determined to be in the best interest of the County to award to the lowest, responsive, respon...

Click here for full text