Legislation Details

File #: 2024-6552    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 11/5/2024 In control: Board of County Commissioners
On agenda: 11/26/2024 Final action:
Title: 24-444, Approve Change Order, Desoto Ditch Bank Hurricane Repairs and Re-stabilization (Public Works)
Attachments: 1. 24-444 Change Order request
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

24-444, Approve Change Order, Desoto Ditch Bank Hurricane Repairs and Re-stabilization (Public Works)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Change Order in the amount of $599,950 for Request for Bid #24-444, Desoto Ditch Bank Hurricane Repairs and Re-stabilization for an updated total amount of $1,265,106.35. This project is for the repairs and re-stabilization of the Desoto ditch bank; and

b) Approve additional 92 days of contract time for an updated contract time of 212 days.

end

budget

Budgeted Action:

No action needed. Grant funding in the amount of $499,962.50 and the required match in the amount of $149,962.50 are included in the FY24 budget for Public Works. Grant funding will be provided by the USDA - NRCS (Unites Sates Department of Agriculture, Natural Resources Conservation Service). Matching funds in the amount of $149,962.50 will be provided from the Hurricane fund 1901.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

This project is for the repairs and re-stabilization of the Desoto ditch bank, which was damaged during Hurricane Ian. Hurricanes Helene and Milton caused further damage to the ditch banks, while under construction, and requires additional stabilization measures to repair and protect the ditch banks. Additional gopher tortoises were also noted at the job site and need to be relocated as per state and federal procedures.

 

The original contract time was 120 days for completion. With the additional 92 days, the updated contract time is 212 days.

 

Therefore, it is recommended to approve Change Order in the amount of $599,950 and an additional 92 days for Request for Bid #24-444, Desoto Ditch Bank Hurricane Repairs and Re-stabilization for an updated total amount of $1,265,106.35 and an updated contract time of 212 days.