Legislation Details

File #: 2025-6656    Version: 1 Name:
Type: Consent Item - Land Use Status: Agenda Ready
File created: 1/2/2025 In control: Board of County Commissioners
On agenda: 1/28/2025 Final action:
Title: FP-21-10-19, Waterview Landing
Attachments: 1. 1-Staff Memo, 2. 2-Presentation, 3. 3-Bond Reduction Request Letter, 4. Waterview FP-21-10-19 First Amended Deverloper's AGR
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Title

title

FP-21-10-19, Waterview Landing

end

Requested Motion/Action

Department Making Request

recommendation

Community Development

Approve a Bond Reduction request and First Amendment to Developer’s Agreement to reduce the amount of the approved surety provided under Bond No. 9392726 in the amount of $3,262,786.86 to $231,154.66 for the completion of the remaining infrastructure for Waterview Landing. The site contains 34.33± acres and is generally located south of Greenway Boulevard, north of the Lake Babcock Drive, west of Bluebird Trail and east of SR 31. The site is located within the boundary of the Babcock Ranch Community Development of Regional Impact (DRI) Increment 1. Located in Commission District I.

Quasi-Judicial

end

Agenda Item Type

Consent

Budgeted Action:

No action needed.

 

Background (Why is this Action Necessary, and What Action will be accomplished)

body

Background:

On behalf of Toll Brothers, Inc., Kimley-Horn is requesting a Bond Reduction and First Amendment to Developer’s Agreement to reduce the amount of the approved surety for Waterview Landing. The subdivision, consisting of 96 lots and six tracts, was granted Final Plat approval by the Board of County Commissioners on September 13, 2023. The plat infrastructure was previously bonded through Fidelity and Deposit Company of Maryland in the amount of $3,262,786.86, which they are requesting be reduced to $231,154.66, consisting of the new Engineer’s Estimate of Probable Cost and 10% bonding amount.

The County Engineer has approved the Engineer’s Opinion of Probable Cost for the new bond amount.

What Action will be accomplished?

If approved, the Developer’s Agreement will be amended. All improvements must be completed per the approved plans to the satisfaction of the County Engineer or a new Developer’s Agreement must be in place and the County will accept the surety provided by Toll Brothers, Inc. (Developer).