Skip to main content
File #: 2025-7700    Version: 1 Name:
Type: Consent Item - Land Use Status: Agenda Ready
File created: 10/30/2025 In control: Board of County Commissioners
On agenda: 11/25/2025 Final action:
Title: FP-15-07-02, Island Lakes at Coco Bay
Attachments: 1. 1-Staff Memo, 2. 2-Presentation, 3. 3-Request Letter, 4. Island Lakes at Coco Bay Recorded DA.pdf, 5. First Amendment to Developer's Agreement.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Title

title

FP-15-07-02, Island Lakes at Coco Bay

end

Requested Motion/Action

Department Making Request

recommendation

Community Development

Lennar Homes, LLC is requesting a Bond Reduction and First Amendment to Developer’s Agreement to reduce the amount of the approved surety provided under Letter of Credit No. FGAC-23354, issued by Fidelity Guaranty and Acceptance Corp., in the amount of $2,599,611.95 to $113,718.00 for the completion of the remaining infrastructure for Island Lakes at Coco Bay. The subdivision, consisting of 222 lots and 17 tracts, was granted Final Plat approval by the Board of County Commissioners on October 24, 2023. The site contains 120.07± acres and is generally located south of San Casa Drive, northeast of Placida Road and west of Winchester Boulevard, in the West County area. Located in Commission District III.

Quasi-Judicial

end

Agenda Item Type

Consent

Budgeted Action:

No action needed.

 

Background (Why is this Action Necessary, and What Action will be accomplished)

body

Background:

On behalf of, Lennar Homes, LLC., Banks Engineering is requesting a Bond Reduction and First Amendment to Developer’s Agreement to reduce the amount of the approved surety for Island Lakes at Coco Bay. The subdivision, consisting of 222 single-family lots and 17 tracts This site was granted Final Plat approval by the Board of County Commissioners on October 24, 2023. The plat infrastructure was previously bonded through Fidelity Guaranty and Acceptance Corp in the amount of $2,599,611.95, which they are requesting be reduced to $113,718.00, consisting of the new Engineer’s Estimate of Probable Cost and 10% bonding amount.

The County Engineer has approved the Engineer’s Opinion of Probable Cost for the new bond amount.

What Action will be accomplished?

If approved, the Developer’s Agreement will be amended. All improvements must be completed per the approved plans to the satisfaction of the County Engineer by April 1, 2027, or a new Developer’s Agreement must be in place and the County will accept the surety provided by Lennar Homes, LLC (Developer).

end