Skip to main content
File #: 2025-6822    Version: 1 Name:
Type: Consent Item - Land Use Status: Agenda Ready
File created: 1/28/2025 In control: Board of County Commissioners
On agenda: 2/25/2025 Final action:
Title: PFP-23-05-02, Babcock Ranch Community Crescent Lakes Phase 2
Attachments: 1. 1-Staff Memo, 2. 2-Presentation, 3. 3-Bond Reduction Request Letter, 4. First Amendment to Developer's Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Title

title

PFP-23-05-02, Babcock Ranch Community Crescent Lakes Phase 2

end

Requested Motion/Action

Department Making Request

recommendation

Community Development

Approve a Bond Reduction request and First Amendment to Developer’s Agreement to reduce the amount of the approved surety provided under Bond No. 024268032 in the amount of $2,557,203.06 to $268,681.05 for the completion of the remaining infrastructure for Babcock Ranch Community Crescent Lakes Phase 2. The site contains 39.78± acres and is generally located south of Bermont Road, north of the County line with Lee County, west of the County line with Glades County and east of Bluebird Trail. The site is within the boundary of the Babcock Ranch Community Development of Regional Impact (DRI) Increment 2, the East County area. Located in Commission District I.

Quasi-Judicial

end

Agenda Item Type

Consent

Budgeted Action:

No action needed.

 

Background (Why is this Action Necessary, and What Action will be accomplished)

body

Background:

On behalf of Meritage Homes of Florida, Inc., Barraco and Associates, Inc. is requesting a Bond Reduction and First Amendment to Developer’s Agreement to reduce the amount of the approved surety for Babcock Ranch Community Crescent Lakes Phase 2. The subdivision, consisting of 173 single-family lots and three tracts, was granted Final Plat approval by the Board of County Commissioners on October 24, 2023. The plat infrastructure was previously bonded through Liberty Mutual Insurance Company in the amount of $2,557,203.06, which they are requesting be reduced to $268,681.05, consisting of the new Engineer’s Estimate of Probable Cost and 10% bonding amount.

The County Engineer has approved the Engineer’s Opinion of Probable Cost for the new bond amount.

What Action will be accomplished?

If approved, the Developer’s Agreement will be amended. All improvements must be completed per the approved plans to the satisfaction of the County Engineer by April 2026, or a new Developer’s Agreement must be in place and the County will accept the surety provided by Meritage Homes of Florida, Inc. (Developer).

end