Title: 05-193, Approve, Amendment 14, Engineering Services – Pirate Harbor Waterway (Public Works)
Attachments: 1. Resolution BA27-286, 2. 05-193 Contract Executed, 3. 05-193 Pirate HarborAmend#1, 4. 05-193 Pirate HarborAmend#2, 5. 05-193 Pirate HarborAmend#3, 6. 05-193 Pirate HarborAmend#4, 7. 05-193 Pirate HarborAmend#5, 8. 05-193 Pirate HarborAmend#6, 9. 05-193 Pirate HarborAmend#7, 10. 05-193 Pirate HarborAmend#8, 11. 05-193 Pirate HarborAmend#9, 12. 05-193 Pirate HarborAmend#10, 13. 05-193 Pirate HarborAmend#11, 14. 05-193 Pirate HarborAmend#12, 15. 05-193 Pirate HarborAmend#13, 16. 05193 Amendment 14 Backup, 17. BA27-286 Pirate Harbor WW, 18. Amendment 14 Pirate Harbor
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

05-193, Approve, Amendment 14, Engineering Services - Pirate Harbor Waterway (Public Works)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Amendment 14 to Contract 05-193, Engineering Services - Pirate Harbor Waterway, with Coastal Engineering Consultants, Inc., of Bonita Springs, Florida, for additional services to increase total by $24,925; and

b) Authorize the Chairman to sign Amendment 14. This amendment is to authorize the firm for permit modification to include a Buffer Zone as an eligible mitigation site and additional technical support; and

c) Approve Resolution for budget adjustment BA27-286 in the amount of $1,706 for seagrass mitigation within Pirate Harbor Waterway MSBU.

end

budget

Budgeted Action:

Approve budget adjustment BA27-286 in the amount of $1,706 amending the FY27 budget for Pirate Harbor Waterway MSBU. Funding is available using reserves from Pirate Harbor Waterway MSBU assessments.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

On May 19, 2005, the Board of County Commissioners approved the ranking and negotiations for the Engineering Services - Pirate Harbor Waterway with Coastal Engineering Consultants, Inc. to provide professional engineering services including, but not limited to, permitting, dredging, removing rock, monitoring, and additional services.

 

This amendment is to authorize the firm for permit modification to include a Buffer Zone as an eligible mitigation site and additional technical support. Tasks are outlined within the attached proposal, dated November 2, 2026.