Title: 11-079, Approve Amendment 4, Fixed Base Automatic Meter Reading System (Utilities)
Attachments: 1. 11-079 Contract Executed, 2. 11-079 Amendment #1 - Executed, 3. 11-079 Amendmemt #2 - Executed, 4. 11-079 Amendmenmt #3 - Executed, 5. Amendment 4 to Contract No. 2011000079
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

11-079, Approve Amendment 4, Fixed Base Automatic Meter Reading System (Utilities)                     

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Amendment #4 to Contract #11-079, Fixed Base Automatic Meter Reading (AMR) System, with Mueller Systems, LLC, of Cleveland, North Carolina, extending the contract up to and including September 30, 2026, and revising the parts listing; and

b) Authorize the Chairman to sign Amendment #4.

end

budget

Budgeted Action:

No action needed. Budgeted in the Utilities Operations and Maintenance Fund - Administrative budget as approved in the FY2025 budget process. Funding for this expenditure comes from rate revenues.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

This is for a Fixed Base Automatic Meter Reading System (AMR) providing AMR service to all of Charlotte County Utilities service areas/customers originally approved by the Board of Commissioners on May 24, 2011.

 

Amendment #1 was in accordance with Article 12.3 of the contract which provided for labor and services necessary to facilitate an accelerated deployment of the AMR system.

 

Amendment #2 was due to Federal funding requirements from FDEP, which stated “Supplementary Conditions for Construction Procurement” must be incorporated into the current AMR project contract.

 

Amendment #3 was for the extension of the current contract through September 30, 2025, and amended the pricing schedule.

 

Amendment #4 is for the updating of the parts listing with new part numbers and contract extension through and including September 30, 2026, with the same contract pricing.

 end