19-156, Amendment 2, Engineering, Design and Construction Administrative Services, Eastport Water Reclamation Facility (Utilities)
end
REQUESTED MOTION/ACTION
recommendation
Recommended Action:
a) Approve Amendment #2 to Contract #19-156, Engineering, Design and Construction Administration Services - Eastport Water Reclamation Facility, with Jones Edmunds & Associates, Inc. in the not to exceed amount of $405,000; and
b) Authorize the Chairman to sign the Amendment.
end
budget
Budgeted Action:
No action needed. Budgeted in the CIP project “East Port WRF Expansion” as approved in the FY25 budget process. Funding will be supplied from the Utility Wastewater Connection Fee Fund.
end
BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)
body
Background:
This is for engineering, design, and construction administration for the expansion of the East Port Water Reclamation Facility (WRF) originally approved by the Board on March 12, 2019.
Amendment #1, approved on December 14, 2021, for the County upgrading the East Port WRF to meet Advanced Wastewater Treatment (AWT) standards to support the County’s goal of improving water quality.
This Amendment request is to allow construction administration and construction observation services for the remaining 19 months of construction. A copy of the original contract and Amendment #1 are attached with a detailed scope of services for this request.