Title: 24-116, Approve, Amendment 1 and 2, Construction Manager at Risk - Fire Stations 3, 6, and 17 (Facilities)
Attachments: 1. 24-116 Signed Contract, 2. Amendment 1 to Contract No. 2024000116 Fire Station 6, 3. Amendment 1 to Contract No. 2024000116 Fire Station 17, 4. c222101 Station 17.Additional 2020 STE, 5. c222101 Station 17.Additional 2020 STE AMENDED 12.9.25, 6. c222102 Station 6 Replacement 2020 STE, 7. c222102 Station 6 Replacement 2020 STE AMENDED 12.9.25, 8. BA26-212 Fire Stations 6 &17 addl funding, 9. Resolution BA26-212.pdf, 10. 2025-12-01 MEMO Justification - Budget & GMP - FIre Station 6, 11. 2025-12-01 MEMO Justification - Budget & GMP - FIre Station 17
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

24-116, Approve, Amendment 1 and 2, Construction Manager at Risk - Fire Stations 3, 6, and 17 (Facilities)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Amendment 1 and Amendment 2 to Contract #24-116, Construction Manager at Risk - Fire Stations 3, 6, and 17, with Wharton-Smith, Inc. for the Guaranteed Maximum Price (GMP) for the management/construction phase of the Fire Stations 6 in the amount of $8,012,035 and Fire Station 17 in the amount of $9,424,095; and

b) Authorize the Chairman to sign Amendment 1 and 2; and

c) Approve Resolution for budget adjustment BA26-212 in the amount of $11,250,843; and

d) Approve Amendment to Capital Improvement Project “Fire Station 6 Replacement” increasing total project by $5,588,255; and

e) Approve Amendment to Capital Improvement Project “Fire Station 17 Additional Tuckers Grade / US41” increasing total project by $5,662,588.

end

budget

Budgeted Action:

Approve budget adjustment BA26-212 in the amount of $11,250,843 amending the FY26 budget for Capital Improvement Project “Fire Station 6 Replacement” from $4,500,000 to $10,088,255 and “Fire Station 17 Additional Tuckers Grade / US41” from $5,690,000 to $11,352,588. Funding is supplied from the 2020 Sales Tax Extension. 

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

On February 27, 2024, the Board approved the ranking and start of negotiations for the Construction Manager at Risk - Fire Stations 3, 6, and 17, with the top ranked firm, Wharton-Smith, Inc.

 

These two (2) Amendments for Phase II, the construction management phase, established the scope and approval of the GMP for Stations 6 and 17, which means the maximum compensation to be paid by the County in providing all work required to complete the project.