File #: 2026-7985    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 2/6/2026 In control: Board of County Commissioners
On agenda: 3/10/2026 Final action:
Title: Adoption of Fiscal Sustainability Plan for East Port Water Reclamation Facility Expansion
Attachments: 1. WW0802K0 Original Agreemenrt CN-370000-Y1707, 2. Charlotte County - WW0802E1, 3. Charlotte County WW0802E1 A1, 4. Charlotte County WW0802E1 A2 Executed, 5. Charlotte County WW0802E1 A3 Executed, 6. FINAL FSP East Port WRF, 7. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Utilities

 

Title
title

Adoption of Fiscal Sustainability Plan for East Port Water Reclamation Facility Expansion

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Resolution adopting the East Port Water Reclamation Facility Expansion Capital Project Fiscal Sustainability Plan (FSP) for inclusion into the County’s Capital Maintenance Programs; and

b) Authorize the Chairman to execute the Resolution.

end

budget

Budgeted Action:

No action needed. The FSP is a documentary obligation of East Port Water Reclamation Facility Expansion Florida Department of Environmental Protection’s (FDEP) Loan Agreement and currently has no funding requirements. Any future funding requirements will be incorporated into the County’s Capital Maintenance Program.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

Approval of this item adopts a Fiscal Sustainability Plan (FSP) for the East Port Water Reclamation Facility Expansion Project. Adoption of the FSP is required to satisfy Clean Water State Revolving Fund (SRF) loan conditions administered by the Florida Department of Environmental Protection (FDEP) for Loan Nos. WW0802E-1 and WW0802K-0.

 

The FSP documents Charlotte County Utilities’ existing financial planning, asset management, and operational practices that support long-term sustainability of the County’s wastewater system.

 

FSP adoption is a required condition of the SRF loans and supports final loan amendment and amortization processing with FDEP. This administrative action does not commit the Board to new expenditures or changes in wastewater rates.