File #: 2025-7224    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 5/30/2025 In control: Board of County Commissioners
On agenda: 6/24/2025 Final action:
Title: Capital Project Amendment for Bissett Community Park
Attachments: 1. BA25-177 Bissett Community Park, 2. c722101 AMENDED Bissett Community Park 6.24.25, 3. c722101 Bissett Community Park, 4. Resolution BA25-177.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Community Services

 

Title
title

Capital Project Amendment for Bissett Community Park

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Resolution for budget adjustment BA25-177 in the amount of $65,000; and

b) Approve amending Capital Improvement Project “Bissett Community Park” increasing total project by $65,000.

end

budget

Budgeted Action:

Approve budget adjustment BA25-177 in the amount of $65,000; amending the total project cost for Capital Improvement Project “Bissett Community Park” from $824,730 to $889,730. Additional funding is needed for completion of Phase 1 Master Plan. Funding is supplied from Capital Projects ad valorem.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

The Community Services department began the master planning process of Bissett Park in 2021. Due to rising cost of materials over the last four years the planned amenities requested and approved through the public outreach process has increased in cost. This amendment will allow for completion of Phase 1.

 end