Recommended Action:
a) Board approval to accept the award from the Florida Department of Transportation (FDOT) Shared Use Non-motorized (SUN) Trail Grant for the Design of Segment 1 along SR776 from US41 to Gillot Blvd. in the amount of $2,535,984.00; and
b) Approve Capital Improvement Project “SUN Trail Cape Haze Pioneer Trail US41-Gillot Blvd”; and
c) Approve Resolution authorizing budget adjustment BA25-172 in the amount of $2,535,984; and
d) Approve Resolution of support for project; and
e) Authorize the Chairman, or designee, to sign any grant related documents.
end
budget
Budgeted Action:
Approve Budget Adjustment BA25-172 in the amount of $2,535,984 and new Capital Improvement Project “SUN Trail Cape Haze Pioneer Trail US41-Gillot Blvd.” Allowable grant expenses will be reimbursed by the Florida Department of Transportation (FDOT). There is no local match required.
end
BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)
body
Background:
Grant Agreement #443602-2-34-01 for the FDOT for SUN Trail Program for the Design of Segment 1 of the SUN Trail Network along SR 776 from US41 to Gillot Blvd.