Title: 25-188, Amendment of Contract, Inspection and Condition Assessment for Wastewater System Pipelines, Manholes and Force Mains (Utilities)
Attachments: 1. 25-188 Complete RFP Package, 2. 25-188 Mead and Hunt, 3. Contract RFP25-188 Inspection & Assessment Wastewater Sys 3-10-2026
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

25-188, Amendment of Contract, Inspection and Condition Assessment for Wastewater System Pipelines, Manholes and Force Mains (Utilities)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve the amended contract for Request for Proposal #25-188, Inspection and Condition Assessment for Wastewater System Pipelines, Manholes and Force Mains, with Mead & Hunt of Fort Myers, Florida; and

b) Authorize the Chairman to sign.

end

budget

Budgeted Action:

No action needed. Budgeted in the Utilities Operations and Maintenance Fund - Operations budget as approved in the FY2026 budget process. Funding for this expenditure comes from rate revenues.

 

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

This project is for the professional services required to provide a Wastewater System Pipeline, Manhole and Force Main, Inspection and Condition Assessment in accordance with the County’s Capacity, Management, Operations and Maintenance Program.

 

On February 10, 2026 the Board approved the contract for this project in the amount of $999,640.   Unfortunately, the contract itself had an error that required correcting. The dollar amount approved by the Board was not reflected properly in the contract that was attached to that approval.  Attached as part of this approval is the corrected contract which reflects the dollar amount of $999,640 as approved by the Board on February 10, 2026.

 end