Skip to main content
File #: 2025-7236    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 6/4/2025 In control: Board of County Commissioners
On agenda: 7/22/2025 Final action:
Title: 24-597, Approve Amendment 1, Burnt Store Water Reclamation Facility Permit Modification & Design (Utilities)
Attachments: 1. 24597 Contract EXECUTED, 2. c351901 Burnt Store WRF Expansion .pdf, 3. Amendment 1 to Contract No. 2024000597
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

24-597, Approve Amendment 1, Burnt Store Water Reclamation Facility Permit Modification & Design (Utilities)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Amendment #1 to Contract #24-597, Burnt Store Water Reclamation Facility Permit Modification & Design, with Kimley-Horn and Associates, Inc., of Raleigh, North Carolina, correcting the contract total from $3,643,523 to $3,739,781; and

b) Authorize the Chairman to sign Amendment #1. 

end

budget

Budgeted Action:

No action needed. Budgeted in Capital Improvement Project “Burnt Store Water Reclamation Facility Expansion” as approved in the FY25 budget process. Funding will be supplied by the Utility Wastewater Connection Fee Fund.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

This is for professional services to complete a major permit modification and provide a design to increase capacity to a minimum of 1.0 million gallons per day for the Burnt Store Water Reclamation Facility, which was originally approved by the Board of County Commissioners on April 8, 2025.

 

It has been discovered that the sum of the 15 project tasks totals listed out on the Fee Schedule (Page 12 of Exhibit A) totals $3,739,781, not the approved amount of $3,643,523. Task 7, CMAR Support Services was not included in the Total Not-to-Exceed Project Fee.

 end