File #: 2025-7571    Version: 1 Name:
Type: Regular Agenda Status: Agenda Ready
File created: 9/22/2025 In control: Board of County Commissioners
On agenda: 10/14/2025 Final action:
Title: 25-214, Amendment 1, Construction Manager at Risk - Burnt Store Water Reclamation Facility, Guaranteed Maximum Price (Utilities)
Attachments: 1. Amendment 1 to Contract No. 20250214, 2. 25-214 Contract EXECUTED, 3. Presentation, 4. Revised Presentation, 5. Final Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Title
title

25-214, Amendment 1, Construction Manager at Risk - Burnt Store Water Reclamation Facility, Guaranteed Maximum Price (Utilities)

end

recommendation

Budget & Admin Services

a) Approve Amendment 1, to Contract 25-214, Construction Manager at Risk - Burnt Store Water Reclamation Facility with Jon F. Swift, Inc. for the Guaranteed Maximum Price (GMP) for the management/construction phase of the project in the amount of $7,905,238.77; and

b) Authorize the Chairman to sign Amendment 1.

**Change, Added attachment - Revised Presentation, 10/09/2025**

**Change, Added attachment - Final Presentation, 10/13/2025**

end

 

Budgeted Action:

No action needed. Budgeted in Capital Improvement Project “Burnt Store Water Reclamation Facility Expansion” as approved in the FY26 budget process. Funding will be supplied by the Utility Wastewater Connection Fee Fund.

 

Background:

body

On March 25, 2025, the Board of County Commissioners approved the ranking and negotiations for the Construction Manager at Risk - Burnt Store Water Reclamation Facility with Jon F. Swift, Inc.

 

This Amendment is for the temporary treatment capacity needed prior to the completion of the improvements to 1.0 MGD at the Burnt Store Water Reclamation Facility at a GMP of $7,905,238.77. It also establishes the scope and approval of the GMP, which means the maximum compensation to be paid by the County in providing all work required to complete the project. The anticipated work/construction is to be at substantial completion by August 31, 2028.