Legislation Details

File #: 2024-6326    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 8/26/2024 In control: Board of County Commissioners
On agenda: 9/10/2024 Final action:
Title: 05-193, Approve, Amendment 13, Engineering Services - Pirate Harbor Waterway (Public Works)
Attachments: 1. 05-193 Executed Contract, 2. 05-193 Amend1 Executed, 3. 05-193 Amend2 Executed, 4. 05-193 Amend3 Executed, 5. 05-193 Amend4 Executed, 6. 05-193 Amend5 Executed, 7. 05-193 Amend6 Executed, 8. 05-193 Amend7 Executed, 9. 05-193 Amend8 Executed, 10. 05-193 Amend9 Executed, 11. 05-193 Amend10 Executed, 12. 05-193 Amend11 Executed, 13. 05-193 Amend12 Executed, 14. Amendment 13 to Contract No. 2005000193
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

05-193, Approve, Amendment 13, Engineering Services - Pirate Harbor Waterway (Public Works)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Amendment #13 to Contract #05-193, Engineering Services - Pirate Harbor Waterway, with Coastal Engineering Consultants, Inc., of Bonita Springs, Florida, for additional services with a change order to increase total by $18,220; and

b) Authorize the Chairman to sign Amendment #13.

end

budget

Budgeted Action:

No action needed. Budgeted in the Pirate Harbor Waterway MSBU as approved in the FY24 budget process. Funding is supplied from Pirate Harbor Waterway MSBU assessments.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

On May 10, 2005, the Board of County Commissioners approved the ranking and negotiations for the Engineering Services - Pirate Harbor Waterway with Coastal Engineering Consultants, Inc. to provide professional engineering services including, but not limited to, permitting, dredging, removing rock, monitoring, and additional services.

 

This amendment is to authorize the firm to conduct the fifth-year seagrass survey of mitigation area for the impacts to seagrasses disturbed during the dredging of the access channel. Tasks are outlined within the attached proposal, dated April 18, 2024.