File #: 2024-6254    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 8/6/2024 In control: Board of County Commissioners
On agenda: 9/10/2024 Final action:
Title: 24-440, Approve Ranking, Golf Course Water Booster Station and Englewood Interconnect Station Upgrades (Utilities)
Attachments: 1. 24-440 Shortlisting, 2. 24-440 Submittal Kimley-Horn, 3. c332209 Golf Course Booster Station Upgrades
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

24-440, Approve Ranking, Golf Course Water Booster Station and Englewood Interconnect Station Upgrades (Utilities)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve the sole proposer for Request for Proposal #24-440, Golf Course Water Booster Station and Englewood Interconnect Station Upgrades: 1st Kimley-Horn, of Sarasota, Florida; and

b) Approve start of negotiations; and

c) Authorize the Chairman to sign the contract after completion of negotiations.

This is the engineering technical services pertaining to evaluation and design of upgrades to the Golf Course Water Booster Station and Englewood Interconnect Station.

end

budget

Budgeted Action:

No action needed. Budgeted in Capital Improvements Project “Golf Course Booster Station Upgrades” as approved in the FY24 budget process. Funding will be supplied by the Utility Water Connection Fee Fund.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

Charlotte County is requesting qualified firms to provide engineering technical services pertaining to evaluation and design of upgrades to the Golf Course Water Booster Station (WBS #2) and Englewood Interconnect Station (WBS #8). The required engineering technical services are to be provided on both a lump sum basis for defined tasks and on a time and material expenses, “not-to-exceed” basis, for other tasks.

 

One proposal was received and evaluated by the Professional Services Committee consisting of Johnny Chamberlain, Project Manager, Utilities; Kelly Slaughter, Project Manager, Public Works; and Justin Dunn, Project Manager, Facilities. A copy of the proposal is attached along with a breakdown of the ranking.

 end