File #: 2025-6982    Version: 1 Name:
Type: Consent Item - Regular Status: Agenda Ready
File created: 3/14/2025 In control: Board of County Commissioners
On agenda: 4/8/2025 Final action:
Title: 19-159, Approve Cancellation, Design - Burnt Store Water Reclamation Facility Replacement/Expansion (Utilities)
Attachments: 1. 19-159 Executed Contract, 2. 19-159 Executed Amendment 1, 3. 19-159 Executed Amendment 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

19-159, Approve Cancellation, Design - Burnt Store Water Reclamation Facility Replacement/Expansion (Utilities)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

Approve the cancellation of Contract #19-159, Burnt Store Water Reclamation Facility Replacement/Expansion, with McKim & Creed, Inc.

end

budget

Budgeted Action:

No action needed. No additional financial impact at this time.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

On February 26, 2019, the Board approved the ranking of Request for Proposal #19-159, Design - Burnt Store Water Reclamation Facility Replacement/Expansion, allowing the start of negotiations and authorizing the Chairman to sign the contract after completion of negotiations.

 

On July 23, 2019, the contract was formally executed (signed) by McKim & Creed, Inc. On June 11, 2024, the Board made the official action to cancel the Expansion bid. And Utilities has now requested to cancel/close this design contract per Contract, Section Article 7, Term/Termination, Item 7.3.  