Title: 25-505, Approve Change Orders #1, 2, and 3, Hansen CIS SaaS Software Cloud (Utilities)
Attachments: 1. 25-505 - Original Agreement, 2. 25-505 - CO #1, 3. 25-505 - CO #2, 4. 25-505 - CO #3, 5. c362405 CCU Business Services Customer Billing and Data Base
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
DEPARTMENT MAKING REQUEST
Budget & Admin Services

Title
title
25-505, Approve Change Orders #1, 2, and 3, Hansen CIS SaaS Software Cloud (Utilities)
end
REQUESTED MOTION/ACTION

recommendation
Recommended Action:
Approve award of Change Orders #1, 2, and 3 for File #25-505, Hansen CIS SaaS Software Cloud Agreement, to Hansen Banner, LLC of Bethlehem, Pennsylvania in the amount of $55,200 for the additional services required for the Cityworks integration.
end
budget
Budgeted Action:
No action needed. Budgeted in the Capital Improvement Project "CCU Business Services Customer Billing" as approved in the FY26 budget process. Funding will be supplied from the Utility Operations & Maintenance Fund.
end

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)
body
Background:
Utilities has requested Change Requests #1, 2, and 3 to File #25-505, Hansen CIS SaaS Software Cloud, in the amount of $55,200 for the additional services required for the Cityworks integration of the software. Change request 01 was incurred due to a change in project scope relating to item #59 in the HansenCIS statement of work relating to the Cityworks integration. The organization has elected to move our Cityworks environment from an on-premises environment to a cloud environment prior to the completion of the Banner/HansenCIS project that is currently in progress. The previously laid out approach in the signed agreement and statement of work with Hansen is no longer viable, thus change requests were furnished by Hansen to mitigate this unforeseen change in scope. Change request #2 is the clarification in the statement of work updating the real time integration deployed to connect to Paymentus. Change Order #3 is reduction of 110 hours for the removal of implementation GAPs.

Original Contract Amount: $951,680.00
Change Request #1 for Cityworks Integration: $77,200.00
Change Request #2 for GAP Payment Vendor Change: $0.00
Change Reques...