Title: 25-483, Award, Bermont Road Bridge Rehabilitations for #010020, 010003, 010016, and 010017 (Public Works)
Attachments: 1. 25-483 Bid Tabulation, 2. 25-483 Bidders Submittal, 3. 25-483 - Plans for Bridge 010020, 4. 25-483 - Plans for Bridge 010003, 5. 25-483 - Plans for Bridge 010016, 6. 25-483 - Plans for Bridge 010017
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

25-483, Award, Bermont Road Bridge Rehabilitations for #010020, 010003, 010016, and 010017 (Public Works)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

Approve award of Request for Bid #25-483, Bermont Road Bridge Rehabilitations (#010020, 010003, 010016, and 010017), to Titan Construction Management, LLC of Tarpon Springs, Florida, for the total amount of $863,587.20. This is to complete the repairs and rehabilitation of four (4) box culverts along Bermont Road.

end

budget

Budgeted Action:

No action needed. Budgeted in the Public Works Bridge Capital Maintenance Plan as approved in the FY25 budget process. Funding is supplied from Capital Projects Fund, ad valorem.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

It is the intent of Charlotte County to secure the services of a Contractor to furnish all materials, labor, equipment, and all other appurtenances required to complete the repairs and rehabilitation of four (4) box culverts along Bermont Road: Bermont Road over Myrtle Slough (010020 and 010003), Shell Creek (010016), and Babcock Drainage (010017). The work includes the concrete and guardrail repairs and channel restoration to the box culverts.

 

Therefore, it has been determined to be in the best interest of the County to award to the lowest, responsive, responsible bidder, Titan Construction Management, LLC of Tarpon Springs, Florida, for the total amount of $863,587.20.

 

Completion time is 75 calendar days with $1,690 per calendar day for liquidated damages.

 end