Title: 21-470, Approve Amendment 1, Construction Manager at Risk - Sheriff's Administration/Hardened 911 Facility (Facilities)
Attachments: 1. 21-470 Signed Contract, 2. BA24-089 SO Admin.911, 3. c892101 Sheriff Support Services (Admin HQ).911, 4. c892101 Amended SO Admin.Hard911 2020 STE..3.12.24, 5. Resolution, 6. Amendment 1 to Contract No. 2021000470
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DEPARTMENT MAKING REQUEST

Budget & Admin Services

 

Title
title

21-470, Approve Amendment 1, Construction Manager at Risk - Sheriff’s Administration/Hardened 911 Facility (Facilities)

end

REQUESTED MOTION/ACTION

 

recommendation

Recommended Action:

a) Approve Amendment #1 to Contract #21-470, Construction Manager at Risk - Sheriff’s Administration/Hardened 911 Facility with Wharton-Smith, Inc. of North Port, Florida for the Guaranteed Maximum Price (GMP) for the management/construction phase of the project in the amount of $37,251,386; and

b) Authorize the Chairman to sign Amendment #1; and

c) Approve Resolution for budget adjustment BA24-089 in the amount of $26,000,000, allocating to Capital Improvement Project “Sheriff Support Services (Admin HQ) & Hardened 911”; and

d) Approve amending Capital Improvement Project “Sheriff Support Services (Admin HQ) & Hardened 911”.

end

budget

Budgeted Action:

Approve budget adjustment BA24-089 in the amount of $26,000,000 amending the FY24 budget for capital improvement project ““Sheriff Support Services (Admin HQ) & Hardened 911” increasing from $19,000,000 to $45,000,000. Funding for the adjustment is supplied from the 2020 Sales Tax Extension.

end

 

BACKGROUND (Why is this Action Necessary, and What Action will be accomplished)

body

Background: 

On September 28, 2021, the Board of County Commissioners approved the ranking and negotiations for the Construction Manager at Risk - Sheriff’s Administration/Hardened 911 Facility.

 

This Amendment for Phase II, the construction management phase, establishes the scope and approval of the GMP, which means the maximum compensation to be paid by the County in providing all work required to complete the project.  The anticipated work/construction is to be completed by January 6th, 2026.